Thursday, December 6, 2012

Reliance Power Limited - RESULTS FOR - Q2 FY 2013 - (Q/E SEP,2012) -GOOD PROGRESS IN PROJECT COMMISSIONING - FUTURE BRIGHT


Reliance Power Limited

Q2 FY 2013 RESULTS REVIEW
(Q/E SEP,2012)

HIGH LIGHTS



Performance highlights

Particulars      :: (Rs.) Q2 FY12-13 :: Q2 FY11-12

Operating Revenues  :: 1,079 cr  :: 488 cr – An increase of 121%

Other Income ::                102 cr  ::   263 cr

Total Income   ::              1,181 cr  ::  751 cr – An Increase of 57%

Net Profit    ::                      240 cr  ::   235 cr

EBITDA   ::                          393 CRORE -  An Increase of 227%


Q2 HIGHLIGHTS

Operating Capacity

Ø  1,200 MW Rosa Power Plant in UP generated 1,655 million units (MUs) in this quarter (as against 1,004 MUs the previous year). – An Increase of 65%

Ø  The first 300 MW unit of the Butibori project has been synchronised and is ready for full load operations.

Ø  The 40 MW Dhursar solar PV plant in Rajasthan generated a record 13.8 million units in this quarter which resulted in a net profit of 6.6 crore.

Capacities under Construction:

Ø  Major construction milestone – Boiler light-up of the first 660 MW, supercritical unit – for the 3960 MW Sasan UMPP. Project to be commissioned five months ahead of schedule.

Ø  Coal production commenced from Sasan coal mines. The Moher and Moher Amlori Extn. mines with a capacity of 20 Million tonnes per year, will be India’s largest coal mine.

Ø  Boiler light-up achieved for the second 300 MW unit of the 600 MW Butibori project in M.H. Project to be fully commissioned by end of this year.

Ø  Civil works is in full swing for the 100 MW Concentrated Solar Power (CSP) project in Dhursar, Rajasthan and the project is expected to be commissioned by May 2013.

Ø  45 MW wind project in MH. is in its final stages of implementation. Project to be commissioned by  end of this year.


PROJECT PORTFOLIO

Power-operation
Power – Operation
Project
No.
Capacity (MW)
Coal based
1
1,500
Solar
1
40


Power - implementation
Power – Implementation
Project
No.
Capacity (MW)
Coal based
5
16,140
Gas based
1
2,400
Solar
1
100
Wind
1
200

Power  - Development

Power –Development
Project
No
Capacity (MW)
Hydroelectric
12
5,292
Coal based
1
~5,000


Resources


Asset
No
Resources
Coal blocks-India
3
~ 2 bn tonnes
Coal mine-Indonesia
3
~2 bn tonnes
CBM blocks
4
193.92 BCM


Projects ::                 SASAN                      :: TILAIYA

Projects
Sasan
Tilaiya
1.     Coal block
Moher, Moher-Amlori extn, Chhatrasal
Kerandari BC
2.     Location
Singrauli,
Madhya Pradesh
Hazaribagh,
Jharkhand
3.     Resources
(Million tonnes)
707
1,229
4.     Peak Production (Million tonnes per annum)
25
40

Note  :  65 million tonnes of annual production can support 16,500 MW.

Ø  This apart, there is the secured Fuel supply (Imported Coal from Indonesia – which can support a capacity of 8000 MW; production to start in 2013

Ø  Fuel is said to be secure for all Projects other than Samalkot. (secure for 91% of capacity);

Ø  Captive fuel for all projects other than Rosa, Butibori, Samalkot (captive fuel for 84% capacity)

Ø  PPAS SIGNED FOR 13,720 mw CAPCITY. 84% Of Generation capacity under Operation and construction is tied up through PPAs.

R Power says – it tries to ensure Low Cost of Generation through –

(i)            No dependence on external Resources other than Rosa, Butibori & Samlakot
(ii)           All Projects other than Rosa & Butibori located at Pit head / well head ensuring control over Costs


Implementing projects ahead of schedule :

Rosa I: 600 MW :  Commissioned 3 months ahead of schedule
Rosa II: 600 MW :  Commissioned 4 months ahead of schedule
Solar PV: 40 MW : Constructed in record time of 129 days
Samalkot: 2,400 MW : Gas turbines ready for commissioning in just 15 months
Butibori: 600 MW  :  First unit synchronized in just 21 months
Sasan: 3,960 MW  :  Boiler light-up in just 23 months

Ø  40 MW Solar PV in Rajastan - India’s largest Solar PV Plant – to provide Power to 75000 households in Mumbai (had a NPT of 10.3 cr in H1 FY 13)

Ø  600MW Butibori MH project – To be commissioned by the end of this year.

Ø  The 3960 NW Sasan UMPP MP : Boiler light up has been achieved in October 2012. Project in Progress.
Ø  R Power expects to commission All Units ahead of Schedule. As far as the Mine is concerned, it is in fast progress mode – and over 85000 MT of coal -  produced.

2400 MW SAMALKOT, AO : HIGH LIGHTS ;

Ø  4 Gas Turbines - ready for Generation. Combined cycle commissioning based on Gas Availability.
Ø  Company is evaluating multiple options for Gas sourcing
Ø  It is planning to set up FSRU in Kakinada in partnership with Shell


100 MW SOLAR CSP, RAJASTHAN

PPA signed with NVVN at a levelized Tariff of Rs.11.97/Unit
All contracts have been awarded.
It is on track to be commissioned by May,2013.

45 MW Vashpet Wind, MH

Entire capacity to be commissioned by the end of this year.


Other projects under development are :

1.    Chitrangi Power Project : 3960 MW : To commence construction after  forest clearance of Chhatrasaal Mines

2.    Tilaiya UPMM & Coal Mines : 3960 MW  :  Progress on all aspects of Project Development; Likewise, in respect of Tilaiya Coal Mines, progress is made on Land acquisition and Mine planning

3.    Hydro Projects  : 5292 MW ::


Project
Location
Capacity (MW)
Tato II
Arunachal Pradesh
700
Siyom
Arunachal Pradesh
1,000
Kalai II
Arunachal Pradesh
1,200
Urthing Sobla
Uttarakhand
400
Emini
Arunachal Pradesh
500
Amulin
Arunachal Pradesh
420
Mihundon
Arunachal Pradesh
400
Purthi
Himachal Pradesh
300
Teling
Himachal Pradesh
94
Shangling
Himachal Pradesh
44
Sumte Kothang
Himachal Pradesh
130
Lara Sumta
Himachal Pradesh
104
Total :: 5,292

Indonesian Coal

Ø  51,000 m of drilling completed in all 3 concessions
Ø  JORC Resources and Reserves certified by Marston, USA
Ø  All major clearances obtained
Ø  Detailed mine plan for commencement of mining prepared
Ø  Coal production to start in 2013

Reliance Power, reported a net profit of 2.4 billion rupees for 2nd Q/E September 30, compared with 2.35 billion rupees for the Q2 of last Year. Net sales more than doubled to 10.79 billion rupees. Its fuel costs more than doubled to 6.37 billion rupees and finance expenses jumped 82.7 percent to 1.37 billion rupees.

Reliance Power generated 1,655 million kilowatt-hours, up 65 percent from the previous year in the quarter from its Rosa plant in Uttar Pradesh.

The first unit at its 3,960 megawatt (MW) Sasan power project and the second unit at Butibori project should be commissioned in the next few weeks.

Two of Reliance Power's projects totalling 6,400 MW have been stalled due to scarcity of cheap fuel and it faces the risk of losing one of those due to a legal wrangle with four state  governments.

Q2 FY 2013 CONSOLIDATED REULTS

Income from operations
(a) Net sales/income from operations Rs.1079.21Cr
Expenses
Cost of materials consumed  : Rs.      646.95 Cr
Employee benefits expense  : Rs.       20.29 Cr
Depreciation :  Rs.71.90 Cr
Other expenses : Rs.19.02  Cr
Total expenses  :  Rs.  758.16  Cr
Profit from operations : Rs.321.05 Cr
Other income Rs.102.24 Cr
Finance costs  : Rs.137.35 Cr
Profit before tax  :  Rs.285.94 Cr
Tax expense    :  Rs.45.72  Cr
Net Profit :  Rs.240.22 Cr ;  onsolidated Net Profit :  Rs.     240.22 Cr
Face Value : Rs.10;  Paid-up equity : Rs.2805.13 Cr
Earnings per share (not annualised):
(a) Basic          .86   ;   (b) Diluted      .86

Current Market Price : Rs.99.60. While the company is making good Progress on operational front, It will take some time, before the EPS can rise to a more respectable figure.

Assuming an EPS of around Rs.4 for current year, the PE Ratio on a price of Rs.96 comes to 24.

The future prospects are bright for Reliance Power, as its Project commissioning is proceeding at a Brisk pace with costs kept under reasonable control. The latest moves by the Union Cabinet for FAST TRACK APPROVALS for power and other Infrastructure projects could be a Major Plus for Reliance Power in the months ahead.

 *  *  *  E  N  D  *  *  *

No comments:

Post a Comment